Water Line Replacement Scheduled to Begin in July

pipe


The City of Watsonville is committed to providing our community with a safe and reliable water supply. In order to better serve our customers, we are continually upgrading and replacing our water lines for multiple reasons: increased system reliability, reduced water losses due to leaks, and to improve water quality.

Next on the Schedule

The next water line replacement project is located throughout the Watsonville Shopping Center. The project will consist of installing one-half-mile of new water mains, new isolation valves, new hydrants, and new domestic services.

The project start date will be no earlier than July 5th, 2016 and the estimated length of the project is 50-working days. The project will consist of two (2) phases:

  • Phase-1:
    • Construction schedule: 7:00 a.m.-4:00 p.m., Monday through Friday
    • Anticipated Duration of Work: 25-working days
    • Location: From Green Valley Rd. through the back alley way (behind CVS and Nob Hill & neighboring businesses) to the south side of the Nob Hill Building
  • Phase-2:
    • Construction schedule: 8:00 p.m.-6:00 a.m. Sunday through Thursday
    • Anticipated Duration of Work: 25-working days
    • Location: – From the south side of the Nob Hill Building across parking lot to the signal light on Main St.

If you have any questions regarding this project, contact Steve Hernandez, Water Operations Supervisor at 768-3194.

This entry was posted on Wednesday, June 22nd, 2016 at 12:59 pm and is filed under City Manager, City of Watsonville, Homepage News, Human Resources, Public Works . You can follow any responses to this entry through the RSS 2.0 feed. Both comments and pings are currently closed.