Water Line Replacement Project – Crescent Dr., Melrose Ave., & Allston Way

The following areas will be affected:

  • Crescent Drive
  • Melrose Avenue
  • Allston Way

The project will consist of the installation of:

  • New water mains
  • Isolation Valves
  • Hydrants
  • Domestic Services

The project will begin on April 10, 2017 and the estimated length of the project is 45 working days. We ask for your patience with the anticipated noise, traffic congestion and any other inconvenience created from this work.

If you have any questions or concerns regarding this project, please contact Steve Hernandez, Water Services Manager at 768-3194.

This entry was posted on Tuesday, April 18th, 2017 at 11:05 am and is filed under City of Watsonville, Homepage News, Public Works . You can follow any responses to this entry through the RSS 2.0 feed. Both comments and pings are currently closed.