Where is the project located?

The project will be taking place on Roache Road from Freedom Boulevard to 400 feet beyond Carey Avenue so expect some possible traffic delays.

When will the project be completed?

The project is expected to begin in early April and finish in early May.

What is being done?

  • Installation – one thousand seventy feet (1,070′) of new 6″ ductile iron water main.
  • New residential services.
  • New hydrants and system isolation valves.

Why is this being done?

The current Roache Road water main is well over 50 years old and historically has had some major mainline breaks. The new water main will reinforce our water system in this area by reducing system disruptions, improving water quality, and increasing system reliability.

Who is doing the work?

The City’s Field Services Division will be fulfilling all design and construction aspects of this project. The project map shows the area where construction will take place.

Who do I contact if I have any questions?

You can contact Steve Hernandez, Water Operations Supervisor at 768-3194.

This entry was posted on Thursday, March 14th, 2013 at 12:40 pm and is filed under City of Watsonville, Community Development, Homepage News, Library, Parks & Community Services, Public Works . You can follow any responses to this entry through the RSS 2.0 feed. Both comments and pings are currently closed.