Freedom Blvd. Reconstruction Update

Repairs of failing sub-base in the number 2 lane against the curb just south of Alta Vista were necessary due to weather and soil conditions. This strip of road softened during paving portion of the project when heavy trucks were required for the job. This is not uncommon in Watsonville due to the soil conditions.

Be aware when driving in this area as re-routing of traffic will be necessary throughout the length of this project.We will continue to update the status of this project as work continues.

If you have questions, contact Patrice Theriot, Principal Engineer at 768-3113.

This entry was posted on Thursday, March 2nd, 2017 at 5:26 pm and is filed under City of Watsonville, Homepage News, Public Works . You can follow any responses to this entry through the RSS 2.0 feed. Both comments and pings are currently closed.